I have built a Gantt chart in excel that allows the entry of start and end dates for tasks (up to 18) and a percent completion. I want to be able to autoscale the time axis based on the minimum and maximum dates of the tasks. Can the scale min and max be calculated from a cell, so that it does not have to be edited manually?
See the file for more info. Some of my data is behind the chart.
Any help is GREATLY appreciated.
See the file for more info. Some of my data is behind the chart.
Any help is GREATLY appreciated.