Not each day. I am counting the projects in my hand based on each serial number. For example it takes 23 days to finish the project with serial number 123456 (6th row in green bars) and within this 23 days I worked on 4 more projects (rows 2, 4, 5 and 7) that may or may not have been finished. Do you see the logic now?Are you looking for something that says how many projects you had on each day within a period?
Here I have created a sample database with a new table that has more rows and from now on we will use it until we get the right query.
Please see the attached database and run the query. The calculated numbers are not what I am expecting to see.
Sorry for late respond to your question. I have my limitations when I am at work, made me to create a sample DB from scratch.