Calling Milo-O-phile

I'm still missing something.

Ok, with Sat. Feb 1, 2003 as the start date, and Wed. Feb 5, 2003 as the only holiday, I count the following days:

Feb
3,5,6,7,10,11,12,13,14,17,18,19,20,21,24,25,26,27,28

Mar
3 is the 20th workday.

Is the code looking for the day following the 20th workday?

:confused: (and maybe just dense this morning).

M
 
Re: I'm still missing something.

Gotcha - the reason for this is when I use the code it will only be used on a Monday to Friday basis therefore I don't expect a date to ever be a Saturday or Sunday.

I can fix it up but I'm busy just now.
 
You ARE a tricky one!!

God!.......A...Duh!

Only I would try to enter a start date that wouldn't apply anyway.

You still need to Dummy proof it for gals like me!

:o

(Sitting on the porch swing and wishing she had just kept quiet)
 
Re: You ARE a tricky one!!

Misty said:
Only I would try to enter a start date that wouldn't apply anyway.

You still need to Dummy proof it for gals like me!

As I said, it's something I use and was just posting to help someone out. On the actual Calendar control, when picking dates, etc I ensure the date is valid.
 
Just to let you know...

Thanks loads Milo-o-phile... it is working brilliantly.. thanks for your patience...
 