Hi all. I would like to know if anybody knows, if it's possible to add the number of hours worked, say 9.5, to a start time, say 07:30, to generate a finish time, in this example 17:00.
This seems a strange question as the response I'll probably get will be, why not have hours worked calculated from the difference between the start and finish time.
the reason for this is people using the database assign hours worked to different tasks which are then totaled for the day i.e Task 1 4hours Task 2 5.5 hours, total for day 9.5 hours. I currently DO work out the correct number of expected hours via the difference between the start and finish time which is highlighted to the user next to the total hours they have entered to ensure the 2 match up, however some users ignor this put in the corrct number of hours worked then don't amend the start and finish times.
This makes my report look extremely messy as hours worked and times worked don't match which means I'm geting moaned at by people using the report as they have to do more work by looking into which is correct, the hours or times.
Its for his reason I wanted to try and get an answer to my original question, is it possible to add hours worked to a start time to get a finish time. Even if the start time is wrong, at least this way the difference between the start and finish time would match the number of hours worked.
For reference, hours worked fields are number (single format) fields, start time field is currently a Date/Time field
Hope this is clear enough and I haven't rambeled to much.
This seems a strange question as the response I'll probably get will be, why not have hours worked calculated from the difference between the start and finish time.
the reason for this is people using the database assign hours worked to different tasks which are then totaled for the day i.e Task 1 4hours Task 2 5.5 hours, total for day 9.5 hours. I currently DO work out the correct number of expected hours via the difference between the start and finish time which is highlighted to the user next to the total hours they have entered to ensure the 2 match up, however some users ignor this put in the corrct number of hours worked then don't amend the start and finish times.
This makes my report look extremely messy as hours worked and times worked don't match which means I'm geting moaned at by people using the report as they have to do more work by looking into which is correct, the hours or times.
Its for his reason I wanted to try and get an answer to my original question, is it possible to add hours worked to a start time to get a finish time. Even if the start time is wrong, at least this way the difference between the start and finish time would match the number of hours worked.
For reference, hours worked fields are number (single format) fields, start time field is currently a Date/Time field
Hope this is clear enough and I haven't rambeled to much.