Any suggestions and best practices on the following.
I have commit times (which are days).
I need to calc the end date based on a start date and the number of days added. Excluding weekends and 10 us holidays.
Example.
Start date is 9/7 and needs to be delivered in 6 days. So I need to calculate the holiday and weekend. So the delivery would be 9/15.
Thanks
I have commit times (which are days).
I need to calc the end date based on a start date and the number of days added. Excluding weekends and 10 us holidays.
Example.
Start date is 9/7 and needs to be delivered in 6 days. So I need to calculate the holiday and weekend. So the delivery would be 9/15.
Thanks